Stokes Basket Drill

  • HAVE CREWS SET UP LADDER AND STOKES BASKET FOR VICTIM REMOVAL
  • USE THE ROOF OF THE FIREHOUSE TO REMOVE A VICTIM OR TWO REITERATE THAT LADDER CONTROL IS KEY TO THIS OPERATION
  • THE LADDER OPERATOR WORKS DIRECTLY WITH THE CONTROL PERSON ON THE ROOF
  • USE A TAG LINE TO CONTROL BASKET



DIRECTIONS

  • USE 150 FEET FEET OF ROPE
  • ATTACH PULLEY SYSTEM TO THE END OF THE LADDER
  • FEED ROPE FROM TOP TO BOTTOM THROUGH PULLEY ON LADDER
  • PULL 9-12 FEET OF ROPE THROUGH PULLEY AND TIE A FIGURE 8 ON A BIGHT. THIS IS YOUR CONNECTION POINT FOR THE STOKES
  • ON THE RUNNING END TIE A FIGURE 8 FOLLOW THROUGH AROUND THE 3 RUNG
  • TAKE THE ROPE BAG TO THE BASE OF THE LADDER
    ON THE BOTTOM RUNG USE 2 WEBBING LOOPS FOR AN ANCHOR.

  • ATTACH 2 PRUSIK CORDS TO THE ROPE AND THEN ATTACH THEM TO THE WEBBING USING A CARABINER

EQUIPMENT

  • 150 FEET OF ½ ROPE
  • STOKES BASKET
  • STOKES BRIDAL
  • LADDER PULLEY
  • 2 PRUSIKS
  • 2 WEBBING LOOPS
  • 2 CARABINERS



STOKES BASKET SET UP
2 PRUSIKS TO A CARBINER TO 2 WEBBING LOOPS ON THE BOTTOM RUNG FOR AN ANCHOR



ROPE AND ATTACHMENT POINTS
STOKES BASKET CONNECTION
FIGURE 8 ON A BIGHT


ROPE AND ATTACHMENT POINTS
9 – 12 FEET OF ROPE BETWEEN KNOTS CONNECTING LADDER AND STOKES


ROPE AND ATTACHMENT POINTS
FIGURE 8 FOLLOW THROUGH
LADDER TIP CONNECTION AT 3RD RUNG


STOKES BASKET AND LITTER
MAKE SURE ADJUSTING NUTS FOR CARABINERS ARE TO THE INSIDE